Asset Management and Facilities Services is working with GenesisSolutions to implement the Maximo 7.6 system. The team from GenesisSolutions will lead AM-FS staff through a series of phases including preparation, design, development, testing, training, and go-live. Throughout the implementation, Genesis will work to ensure that we develop a system that meets our business requirements and that is usable, sustainable, and maintainable.
Project Timeline
Key Phases | Target Completion | Status |
Project Kick-off | February 2016 | Complete |
Core Team Training | Early March 2016 | Complete |
As-Is Business Process Review | Mid March 2016 | Complete |
To-Be Business Process Review | Mid April 2016 | Complete |
Design | Early May 2016 | Complete |
Development | September 2016 | Complete |
Testing | September 2016 | Complete |
Training | September 2016 | Complete |
Go-Live (Core) | October 2016 | Complete |
Mobile Pilot | May - June 2017 | In Progress |
Mobile Go-Live (Phased) | Mid July 2017 - October 2017 | In Progress |