Maximo Implementation Plan

Asset Management and Facilities Services is working with GenesisSolutions to implement the Maximo 7.6 system.  The team from GenesisSolutions will lead AM-FS staff through a series of phases including preparation, design, development, testing, training, and go-live.  Throughout the implementation, Genesis will work to ensure that we develop a system that meets our business requirements and that is usable, sustainable, and maintainable.

Project Timeline

Key Phases Target Completion Status
Project Kick-off February 2016 Complete
Core Team Training Early March 2016 Complete
As-Is Business Process Review Mid March 2016 Complete
To-Be Business Process Review Mid April 2016 Complete
Design Early May 2016 Complete
Development September 2016 Complete
Testing September 2016 Complete
Training September 2016 Complete
Go-Live (Core) October 2016 Complete
Mobile Pilot May - June 2017 In Progress
Mobile Go-Live (Phased) Mid July 2017 - October 2017 In Progress