Submit for a final inspection, both with the Building Department and the Campus Fire Marshal. Once you've corrected any prior deficiencies, and passed a final inspection (or corrected any punchlist items generated during your final inspection) you can start working on your closeout documents:
- As-Built and/or Record Drawings (Record Drawings if multiple disciplines involved; As-Built Drawings by trade)
- Operations and Maintenance Manuals
- Warranties/guarantees
- California Energy Code (Title 24 Pt. 6) compliance documentation, including
- Commissioning by certified commissioning agent (lighting/HVAC)
- Installation certificates completed by installer/contractor guaranteeing fixtures/appliances were installed as outlined in permit documents
You'll receive a Certificate of Occupancy upon the approval of Building Official and Campus Fire Marshal.
Note: projects must submit all required close-out documents before retention can be released or final payment made.