Maximo Go Live in Seven Weeks

September 26, 2016

FS colleagues:

Thanks to all of you for your continued engagement in the Maximo implementation. We are nearing the final phases of the project and are on track for a Mid-November go live.

Here are a few important updates about the project:

System Design – The design of the system has been reviewed and it is currently being developed/configured. We are on track to complete development and start User Acceptance Testing (UAT) on October 24. Key users from each group will be involved in the UAT, so please watch your email/calendar for...

Implementation Partner Selected

February 22, 2016

In Fall 2015, we began the search of a partner to assist us with the implementation of Maximo, an enterprise asset management and work management tool to replace our current system. I am pleased announce that we have successfully completed the Request For Proposal process and selected GenesisSolutions as our implementation partner. We are working with the team from Genesis Solutions to build a project timeline and are tentatively planning to have their team on site the week of February 22, 2016. In early March,...

Maximo Project Update

March 21, 2016

Thanks to all of you for your participation in numerous sessions of Maximo Implementation since the last week of February. The review of our current business processes is complete and we are now working towards the next milestone of designing our future business processes. Your participation in these sessions is essential as the information we provide the implementation team and the decisions that we will make at these meetings will determine the success of our system. It is crucial that we have the benefit of your knowledge and experience.

We now have a demo site ready...

Maximo Process Review Complete!

April 25, 2016

FS colleagues:

Once again, thanks to all of you for your participation in the many sessions on Maximo implementation since February. The Genesis team is extremely appreciative of the input, creativity and engagement which you have brought to these sessions.

Updates:

Business processes - We wrapped up with our future business process sessions last week. All the discussions and decisions we have taken collectively during the business process sessions are being documented as future process maps and requirements which will be approved before we move into the design...